JSW Steel’s Dolvi Steel Plant Expansion To Be Completed Soon

The expansion comprises of installation of a 4.5 mtpa blast furnace, along with a steel melt shop and hot strip mill, each of 5 mtpa capacities.

SEATTLE (Scrap Monster): The expansion works at JSW Steel’s Dolvi Works plant is expected to be completed by March next year.

The steel plant in that state of Maharashtra in western India has a production capacity of 5 million tonnes per annum (mtpa). The investment of approximately INR 15,000 crore is aimed at doubling the plant’s capacity to nearly 10 mtpa, said Jayant Acharya, Director-Commercial Marketing and Corporate Strategy, JSW Steel.

The expansion works were affected by the outbreak of the Covid-19 pandemic. The company was forced to suspend works, on account of multiple reasons including workplace and travel restrictions. It had received government approval to restart the works only towards end-April this year. The expansion works would have completed earlier than this, except for the Covid-19-induced delay.

ALSO READ:

JSW Steel USA to Ramp Up Mingo Junction and Baytown Mills

Fitch Ratings Foresees Contraction in Indian Steel Demand in FY21

The expansion comprises of installation of a 4.5 mtpa blast furnace, along with a steel melt shop and hot strip mill, each of 5 mtpa capacities. In addition, the plant will have an 8 mtpa pellet plant and four kilns of lime calcinations plants and a captive plant. The completion of the expansion project will lift JSW Steel’s total steelmaking capacity to 23.1 mtpa.

The company press release stated that almost 95% work in connection with the expansion project has been completed already.