Norske Skog to Start Containerboard Production at Golbey Mill in Q1 2025
Containerboard production at Golbey will become part of the Packaging Paper accounting segment from the Q1 2025.
SEATTLE (Scrap Monster): Containerboard production at Norske Skog Golbey in France is expected to start during the Q1 2025, previously the second half of 2024.
Commissioning of roll warehouse, containerboard winder, and the effluent station is ongoing. In addition, pre-commissioning (I/O check) has started for the OCC drum pulper and will start in early October for the paper machine (PM1). However, work relating to piping and electrical cabling has taken longer than planned. The net investment amount is increased to Euro 320 million from previous Euro 300 million as a result of the revised timeline and the addtional work required.
Containerboard production at Golbey will become part of the Packaging Paper accounting segment from the Q1 2025.
The BCTMP main study at Norske Skog Saugbrugs has commenced with support from engineerng consultants and vendor dialogues. Final investment decision is still expected during the first half of 2025.
“Completion of the the containerboard project at Golbey remains a top priority across the Norske Skog group and for me personally. We will do our utmost to complete the project within the updated time frame and budget, and look forward to start customer deliveries. This project has provided us with important lessons that will be implemented in the BCTMP project at Saugbrugs,” says CEO Geir Drangsland.
Norske Skog is a leading producer of publication paper with strong market positions and customer relations in Europe and Australasia.
Courtesy: www.lesprom.com
Scrap Metal Prices
Copper Scrap | ||
Alternator | 0.39 | $US/Lb |
#1 Copper Bare Bright | 3.99 | $US/Lb |
Aluminum Scrap | ||
356 Aluminum Wheels (Clean) | 0.74 | $US/Lb |
6061 Extrusions | 0.64 | $US/Lb |
Steel Scrap | ||
#1 Bundle | 360.00 | $US/MT |
#1 Busheling | 380.00 | $US/MT |
Electronics Scrap |